July 10, 2026 – San Diego, CA
Construction at Riverwalk continues to advance across all components of the development, with key structural milestones achieved and multiple buildings progressing simultaneously.
Building A reached an important milestone with wood framing underway since mid-June and structural concrete nearing completion in mid-July. Building C has also entered the vertical construction phase, with framing activities beginning in early July and concrete progress continuing through the month. Meanwhile, work on Buildings B and D is focused on concrete foundations, laying the groundwork for the next phase of vertical construction.
Significant progress is also being made within the retail village, where structural steel work began at the start of July, helping to shape the future commercial core of the project.
Overall, the project is now approximately 21% complete, with 97% bought out, demonstrating strong alignment across procurement and field operations.
Looking Ahead
In the coming weeks, construction efforts will focus on MEP interior rough-in for Buildings A and C, continued progress on Building B and D foundations and underground MEP rough in, and ongoing structural steel installation in the retail village. These next steps will further drive momentum as Riverwalk continues to take shape.
—
Milender White is a full-service general contractor dedicated to delivering outstanding results on every project, unsurpassed service to clients, and superb career opportunities – with a total commitment to safety, quality and integrity. MW is part of the Graham Group of Companies, headquartered in Calgary, AB. Together as One Graham, we provide our clients with a fully-integrated service offering that creates certainty and peace of mind throughout the entire project life cycle. Visit us at www.milenderwhite.com.