Milender White (MW) partially demolished an existing slab on the pan observation deck at DIA. The deck, supported from below by structural steel beams and columns, was first saw cut into six sections. Rigging for each section was installed before final saw cuts were made. The team then lowered each section 40’ to the ground over a period of two days. The sections ranged in weight from 14,000 lbs. to 65,000 lbs.
MW analyzed three methods of completing the demolition. Following discussions with DIA, the engineer of record, and the subcontractors, we developed a work plan detailing the safest and most efficient approach.
Thanks to the extensive pre-planning and onsite supervision, the work was completed with no issues. Lowering full sections to the ground for demolition instead of demolishing the deck in place resulted in increased productivity, enhanced quality control, and zero injuries or incidents.